400,000SF Major Trucking Terminal

Watch us at work

When a major trucking company needed to replace a 400,000SF terminal parking lot, our crews took care of business. We value engineered, excavated, installed base, and poured new concrete.

Location
Chicago, IL
Project Timeline
4 phases, 5 days/phase
Services Rendered
Self-performed engineering, excavation, and installation

To complete the project without disruption of the trucking terminal operations, the scope of work was scheduled into four 5-day phases with 1000 yards of concrete poured per day in each phase.